Starting in late 2006 we began researching alternatives for our 2-4 year old playgrounds. After a number of almost done deals, we made a decision to go with an artificial turf and to cover more playground than originally intended. Following is a history of that project with detail and pictures.
In May 2007 we contracted with Versasport to cover the two fall zones on the 2-4 yr old playground and the fall zone on the schoolager playground. We also decided to put down the artificial turf an the entire playground used by suites 300-450.
We also made plans to add a basketball court on the schoolage playground and cover a few other areas with concrete that were mud and trip hazards. Our original intent was to add new sod to parts of the schoolage playground. When the wrong ‘turf’ was shipped to the school, we took the opportunity to buy some of it to cover most of the schoolage playground. We did this portion ourselves.
Pictures of the process are below:
You can visit our main website at www.krkms.com